Cold Springs pipeline rehabilitation
Spanish Fork is rehabilitating one of the two pipelines that carry spring water down Cold Springs canyon, and Phase 2 includes a crossing under a railroad. The pipeline was out of service during the work. On Oct. 6 the council voted 5-0 to approve a $519,902.28 change order, a mid-project addition to the contractor's agreement. About $144,000 pays to fill an abandoned pipe section under the tracks with flowable concrete and add a drain valve, as the railroad requires. The other roughly $376,000 is an estimate of extra railroad flagging and observation by RailPros, on top of about $300,000 the original bid already carried for that work. Public Works Director Cory Pierce called the figure conservative and said it could come in lower. The contractor was working five 12-hour days a week to shorten the railroad observation period, and on Oct. 6 it expected the remaining work to take about ten days. That was a dated estimate, so no completion record is in the posted minutes. Costs come from the Water Fund; the project also uses a $2 million state grant.
- Where it stands
- Under construction
- Type
- Public project
- Status evidence date
- Tue, Oct 6
- Location
- Cold Springs water transmission pipeline
Updates
October 6, 2026
Phase 2 change order of $519,902.28 approved 5-0. The contractor expected to finish in about ten days. Source
Follow the money and project delivery
Cold Springs pipeline rehabilitation
- Council action
Under construction according to the dated project source. Record → · Oct. 6, 2026
- Money in the record
change-order: $519,902.28 — Railroad flagging and observation, filling the abandoned pipe under the railroad and a drain valve, Cold Springs Pipeline Rehabilitation Phase 2 Record → · Oct. 6, 2026
- Signed agreement and payments
Execution and project-level disbursements are not verified by this tracker. They require separate records; meeting approval alone does not establish either.
- Work and operating costs
Check the linked records for completion and recurring operating costs; this tracker does not verify them. Record →
Every hearing and vote
October 6, 2026 · City Council
Cold Springs Pipeline Rehabilitation Phase 2 change order
Approved · 5-0
The council approved a $519,902.28 change order on the Cold Springs pipeline rehabilitation. About $144,000 covers railroad requirements to fill an abandoned pipe section under the railroad with flowable concrete and add a drain valve. The remaining estimate of about $376,000 is mainly additional railroad flagging and observation by RailPros. Public Works Director Cory Pierce said the figure is a conservative estimate and could come in lower.
- The original bid included about $300,000 for railroad flagging and observation
- The contractor was working five 12-hour days a week to shorten the railroad observation period
- One of the two Cold Springs pipelines was out of service during rehabilitation; the contractor expected to finish the remaining work in about ten days